[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117574":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117574,789,1,"单选题","施工组织总设计的编制程序中，计算主要工种工程的工程量之后紧接着的工作应是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定施工的总体部署",true,{"key":16,"text":17,"correct":18},"B","编制施工总进度计划",false,{"key":20,"text":21,"correct":18},"C","计算主要技术经济指标",{"key":23,"text":24,"correct":18},"D","施工总平面图设计","2021\u002F2020教材P26页 三、施工组织总设计的编制程序1.收集和熟悉编制施工组织总设计所需要的有关资料和图纸；2.计算工程量；3.确定总体部署；4.拟订施工方案；5.施工总进度计划；6.资源需求量计划；7.施工准备工作计划；8.施工总平面图计划；9.计算主要技术经济指标。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]