[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117567":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117567,789,1,"单选题","某公司计划编制施工组织设计，已收集和熟悉了相关资料，调查了项目特点和施工条件，计算了主要工种的工程量，确定了施工的总体部署，接下来应该进行的工作是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拟定施工方案",true,{"key":16,"text":17,"correct":18},"B","编制施工总进度计划",false,{"key":20,"text":21,"correct":18},"C","编制资源需求量计划",{"key":23,"text":24,"correct":18},"D","编制施工准备工作计划","2021\u002F2020教材P26页 施工组织总设计的编制程序为：收集和熟悉有关资料和图纸并进行项目特点和施工条件的调查研究；计算主要工种的工程量；确定施工总体部署；拟定施工方案；编制施工总进度计划；编制资源需求量计划；编制施工准备工作计划；施工总平面图设计；计算主要技术经济指标。 虽然编制过程中有些工作顺序可以变动，但是没有施工方案，就无法编制进度计划，没有进度计划，就无从确定资源需求，进而无法进行施工准备。所以，首先应拟定施工方案，选项A正确。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]