[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117566":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117566,789,1,"单选题","某新建办公楼工程，地上28层，地下2层，并设有大型设备层，地下室标高-17. 5m，地下情况复杂，施工困难，针对该情况，施工单位应当编制()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工规划",false,{"key":16,"text":17,"correct":14},"B","单位工程施工组织设计",{"key":19,"text":20,"correct":14},"C","施工组织总设计",{"key":22,"text":23,"correct":24},"D","分部分项工程施工组织设计",true,"2021\u002F2020教材P25页 对于工程中某些特别重要的、技术复杂的，或采用新工艺、新技术施工的分部（分项）工程应当编写分部（分项）工程施工组织设计。该深基坑的施工技术复杂，施工困难，因此，应当编写分部（分项）工程施工组织设计。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]