[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117560":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117560,789,1,"单选题","施工组织总设计包括如下工作：①编制资源需求量计划；②编制施工总进度计划；③施工总平面图设计；④拟订施工方案。其正确的工作顺序是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①一②一③一④",false,{"key":16,"text":17,"correct":18},"B","④一②一①一③",true,{"key":20,"text":21,"correct":14},"C","①一③一②一④",{"key":23,"text":24,"correct":14},"D","④一①一②一③","2021\u002F2020教材P26页 施工组织设计中的工作有些顺序不可逆转：(1)拟订施工方案后才可编制施工总进度计划（因为进度的安排取决于施工的方案）；(2)编制施工总进度计划后才可编制资源需求量计划（因为资源需求量计划要反映各种资源在时间上的需求）。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]