[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117559":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117559,789,1,"单选题","施工组织总设计包括如下工作：①计算主要工种工程的工作量；②编制施工总进度计划；③编制资源需求量计划；④拟定施工方案，则其正确的工作顺序是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②③④",false,{"key":16,"text":17,"correct":18},"B","①④②③",true,{"key":20,"text":21,"correct":14},"C","①③②④",{"key":23,"text":24,"correct":14},"D","④①②③","2021\u002F2020教材P26页 施工组织总设计的编制程序如下所示：(1)收集和熟悉编制施工组织总设计所需的有关资料和图纸，进行项目特点和施工条件的调查研究；(2)计算主要工种工程的工程量；(3)确定施工的总体部署；(4)拟定施工方案；(5)编制施工总进度计划；(6)编制资源需求量计划；(7)编制施工准备工作计划；(8)施工总平面图设计；(9)计算主要技术经济指标。应该指出，以上顺序中有些顺序必须这样，不可逆转，如：(1)拟订施工方案后才可编制施工总进度计划因为进度的安排取决于施工的方案(2)编制施工总进度计划后才可编制资源需求量计划（因为资源需求量计划要反映各种资源在时间上的需求)。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]