[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117557":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117557,789,1,"单选题","下列分部（分项）工程中，需要编制分部（分项）工程施工组织设计的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","零星土石方工程",false,{"key":16,"text":17,"correct":14},"B","场地平整",{"key":19,"text":20,"correct":14},"C","混凝土垫层工程",{"key":22,"text":23,"correct":24},"D","定向爆破工程",true,"2021\u002F2020教材P25页 分部（分项）工程施工组织设计是针对某些特别重要的、技术复杂的，或采用新工艺、新技术施工的分部（分项）工程，如深基础、无粘结预应力混凝土、特大构件的吊装、大量土石方工程、定向爆破工程等为对象编制的，其内容具体、详细，可操作性强，是直接指导分部（分项）工程施工的依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]