[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117551":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117551,789,1,"单选题","某施工企业编制某建设项目施工组织总设计，先后进行了相关资料的收集和调研、主要工种工程量的计算、施工总体部署的确定等工作，接下来应进行的工作是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工总进度计划的编制",false,{"key":16,"text":17,"correct":18},"B","施工方案的拟定",true,{"key":20,"text":21,"correct":14},"C","资源需求量计划的编制",{"key":23,"text":24,"correct":14},"D","施工总平面图的设计","2021\u002F2020教材P26页 施工组织总设计的编制通常采用如下程序： 1）收集和熟悉编制施工组织总设计所需的有关资料和图纸，进行项目特点和施工条件的调查研究； 2）计算主要工种工程的工程量； 3）确定施工的总体部署； 4)拟订施工方案; 5）编制施工总进度计划； 6）编制资源需求量计划； 7）编制施工准备工作计划； 8）施工总平面图设计； 9）计算主要技术经济指标。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]