[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117547":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117547,789,1,"单选题","单位工程施工组织设计是以( )为对象编制的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","整个建设工程项目",false,{"key":16,"text":17,"correct":14},"B","某些特别重要的工程",{"key":19,"text":20,"correct":21},"C","单位工程",true,{"key":23,"text":24,"correct":14},"D","分部分项工程","2021\u002F2020教材P25页 单位工程施工组织设计是以单位工程（如一栋楼房、一个烟囪、一段道路、一座桥等）为对象编制的，在施工组织总设计的指导下，由直接组织施工的单位根据施工图设计进行编制，用以直接指导单位工程的施工活动，是施工单位编制分部（分项工程施工组织设计和季、月、旬施工计划的依据。单位工程施工组织设计根据工程规模和技术复杂程度不同，其编制内容的深度和广度也有所不同。对于简单的工程，般只编制施工方案，并附以施工进度计划和施工平面图。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]