[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117537":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117537,789,1,"单选题","项目投资控制、进度控制和质量控制工作编码的基础是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","任务分工表",false,{"key":16,"text":17,"correct":14},"B","合同结构图",{"key":19,"text":20,"correct":21},"C","项目结构图和项目结构的编码",true,{"key":23,"text":24,"correct":14},"D","组织结构图","2021\u002F2020教材P12页 项目结构的编码依据项目结构图，对项目结构的每一层的每一个组成部分进行编码。项目结构的编码和用于投资控制、进度控制、质量控制、合同管理和信息管理等管理工作的编码有紧密的有机联系，但它们之间又有区别。项目结构图和项目结构的编码是编制上述其他编码的基础。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]