[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117536":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117536,789,1,"单选题","通过树状图的方式对一个工程的结构层逐层分解以反映该工程的所有工作任务的组织工具应当是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工作流程图",false,{"key":16,"text":17,"correct":14},"B","工作任务分工表",{"key":19,"text":20,"correct":21},"C","项目结构图",true,{"key":23,"text":24,"correct":14},"D","组织结构图","2021\u002F2020教材P9页 项目结构图（Project Diagram，或称WBS图2Z101021-1项目结构图—Work Breakdown Structure)是一个组织工具，它通过树状图的方式对一个项目的结构进行逐层分解，以反映组成该项目的所有工作任务",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]