[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117533":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117533,789,1,"单选题","某建设项目管理公司的项目部，根据该项目特点制定了投资控制、进度控制、质量控制、合同管理等工作流程。这些工作流程组织属于()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","物质流程组织",false,{"key":16,"text":17,"correct":18},"B","管理工作流程组织",true,{"key":20,"text":21,"correct":14},"C","信息工作流程组织",{"key":23,"text":24,"correct":14},"D","一般作业流程组织","2021\u002F2020教材P22页 管理工作流程组织又包括投资控制、进度控制、合同控制等流程。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]