[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117519":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117519,789,1,"单选题","某工程进度发生延误，项目经理为加快进度，提出一班工作制改为两班工作制，增加夜班工作，增加施工设备和改变施工方法等方案，这属于管理职能中的（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","筹划",true,{"key":16,"text":17,"correct":18},"B","决策",false,{"key":20,"text":21,"correct":18},"C","执行",{"key":23,"text":24,"correct":18},"D","检查","2021\u002F2020教材P20页 筹划——加快进度有多种可能的方案，如改一班工作制为两班工作制，增加夜班作业，增加施工设备或改变施工方法，针对这几个方案进行比较。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]