[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117516":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117516,789,1,"单选题","某建设公司准备实施一个地铁1号线项目的施工任务，开工前项目经理组织相关人员对项目结构进行逐层分解，需要用()来反映组成项目的所有工作任务",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工作流程图",false,{"key":16,"text":17,"correct":14},"B","工作任务分工表",{"key":19,"text":20,"correct":14},"C","组织结构图",{"key":22,"text":23,"correct":24},"D","项目结构图",true,"2021\u002F2020教材P9页 一、项目结构图项目结构图是一个组织工具，它通过树状图的方式对一个项目的结构进行逐层分解，以反映组成该项目的所有工作任务。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]