[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117515":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117515,789,1,"单选题","编制施工管理任务分工表，涉及的事项有：①确定工作部门或个人的工作任务；②项目管理任务分解；③编制任务分工表，则正确的编制程序是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②③",false,{"key":16,"text":17,"correct":18},"B","②①③",true,{"key":20,"text":21,"correct":14},"C","③②①",{"key":23,"text":24,"correct":14},"D","②③①","2021\u002F2020教材P17页 在项目管理任务分解的基础上，明确项目经理和上述管理任务主管工作部门或主管人员的工作任务，从而编制工作任务分工表。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]