[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117507":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117507,789,1,"单选题","施工管理是由多个环节组成的过程，其正确的过程为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","提出问题-执行-决策-筹划-检查",false,{"key":16,"text":17,"correct":18},"B","提出问题-筹划-决策-执行-检查",true,{"key":20,"text":21,"correct":14},"C","提出问题-筹划-检查-决策-执行",{"key":23,"text":24,"correct":14},"D","提出问题-检查-决策-筹划-执行","2021\u002F2020教材P19页 施工管理是由多个环节组成的，即：1.提出问题；2.筹划；3.决策；4.执行；5.检查。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]