[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117497":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117497,789,1,"单选题","达强工程公司承揽了月泉住宅小区建设项目。开工前，该项目的项目经理编制工作任务分工表，首先要对各项管理任务进行( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","系统整合",false,{"key":16,"text":17,"correct":18},"B","详细分解",true,{"key":20,"text":21,"correct":14},"C","整体归纳",{"key":23,"text":24,"correct":14},"D","综合评价","2021\u002F2020教材P17页 在编制项目管理任务分工表前，应结合项目特点对项目实施各阶段的费用（投资或成本）控制、进度控制、质量控制、合同管理、信息管理和组织与协调等管理任务进行详细分解。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]