[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117489":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117489,789,1,"单选题","项目结构图通过树状图的方式对一个项目结构进行逐层分解，以反映组成该项目的所有（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工作部门",false,{"key":16,"text":17,"correct":14},"B","工作人员",{"key":19,"text":20,"correct":21},"C","工作任务",true,{"key":23,"text":24,"correct":14},"D","工作单位","2021\u002F2020教材P9页 项目结构图（Project Diagram，或称WBS――Wk Breakdown Structure）是一个组织工具，它通过树状图的方式对一个项目的结构进行逐层分解，以反映组成该项目的所有工作任务。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]