[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117484":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117484,789,1,"单选题","在项目管理任务分解的基础上，明确项目经理和进度控制管理任务主管工作部门或主管人员的工作任务，从而编制()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作任务分工表",true,{"key":16,"text":17,"correct":18},"B","项目组织设计文件",false,{"key":20,"text":21,"correct":18},"C","项目工作流程图",{"key":23,"text":24,"correct":18},"D","项目管理职能分工表","2021\u002F2020教材P17页 在项目管理任务分解的基础上，明确项目经理和上述管理任务主管工作部门或主管人员的工作任务，从而编制工作任务分工表。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]