[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117467":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117467,789,1,"单选题","项目经理王某在工作中发现由于某些工作之间缺乏联系，导致多付给分包商多项费用。对此，王某组织有关人员对费用控制工作之间的逻辑关系进行调整。王某的工作应当基于（）进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作流程图",true,{"key":16,"text":17,"correct":18},"B","项目结构图",false,{"key":20,"text":21,"correct":18},"C","合同结构图",{"key":23,"text":24,"correct":18},"D","组织结构图","2021\u002F2020教材P13页 工作流程组织图反映一个组织系统中各项工作之间的逻辑关系，是一种动态关系。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]