[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117459":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117459,789,1,"单选题","下列关于项目结构分解的说法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目结构分解没有既定的模式",true,{"key":16,"text":17,"correct":18},"B","对同一个项目其项目结构分解的方法是唯一的",false,{"key":20,"text":21,"correct":18},"C","单体工程不必进行项目结构分解",{"key":23,"text":24,"correct":18},"D","工业建设项目通常按照建设时间对项目结构进行分解","2021\u002F2020教材P11页 综上所述，项目结构分解并没有统一的模式，但应结合项目的特点并参考以下原则进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]