[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117450":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117450,789,1,"单选题","在某纺织职业技术学校新区建设中，总承包商的项目经理在开工前组织有关人员对项目结构进行了逐层分解。这项工作所采用的组织工具应是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目组织结构图",false,{"key":16,"text":17,"correct":18},"B","项目结构图",true,{"key":20,"text":21,"correct":14},"C","工作流程图",{"key":23,"text":24,"correct":14},"D","合同结构图","2021\u002F2020教材P9页 项目结构图：对一个项目的结构进行逐层分解，以反映组成该项目的所有工作任务（该项目的组成部分）@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]