[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117442":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117442,789,1,"单选题","项目管理任务分工表的编制程序包括：①编制任务分工表；②进行项目管理任务分解；③明确各工作部门或个人的工作任务。其正确的顺序是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","①—②—③",false,{"key":16,"text":17,"correct":14},"B","②—①—③",{"key":19,"text":20,"correct":14},"C","③—②—①",{"key":22,"text":23,"correct":24},"D","②—③—①",true,"2021\u002F2020教材P17页 在项目管理任务分解的基础上，明确项目经理和上述管理任务主管工作部门或主管人员的工作任务，从而编制工作任务分工表。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]