[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117433":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117433,789,1,"单选题","在（）之前，应结合项目的特点，对项目实施各阶段的费用控制、进度控制、质量控制、合同管理、信息管理和组织与协调等管理任务进行详细分解。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制管理职能分工表",false,{"key":16,"text":17,"correct":18},"B","编制项目管理任务分工表",true,{"key":20,"text":21,"correct":14},"C","绘制组织结构图",{"key":23,"text":24,"correct":14},"D","绘制工作流程图","2021\u002F2020教材P21页 施工管理的工作任务分工一、工作任务分工每一个建设项目都应编制项目管理任务分工表，这是一个项目的组织设计文件的一部分。在编制项目管理任务分工表前，应结合项目的特点，对项目实施各阶段的费用控制、进度控制、质量控制、合同管理、信息管理和组织与协调等管理任务进行详细分解。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]