[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117432":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117432,789,1,"单选题","采用项目结构图对建设工程项目进行分解时，同一个建设工程项目可有不同的项目结构的分解方法，应与将采用的( )结合。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","组织结构",false,{"key":16,"text":17,"correct":14},"B","工程流程",{"key":19,"text":20,"correct":14},"C","职能结构",{"key":22,"text":23,"correct":24},"D","合同结构",true,"2021\u002F2020教材P9页 同一个建设工程项目可有不同的项目结构的分解方法，项目结构的分解应和整个工程实施的部署相结合，并和将采用的合同结构相结合。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]