[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117424":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117424,789,1,"单选题","供货方作为项目建设的一个参与方，其项目管理工作主要在()阶段进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工",true,{"key":16,"text":17,"correct":18},"B","设计准备",false,{"key":20,"text":21,"correct":18},"C","设计",{"key":23,"text":24,"correct":18},"D","动用前准备","2021\u002F2020教材P4页 供货方的项目管理工作主要在施工阶段进行，但它也涉及设计准备阶段、设计阶段、动用前准备阶段和保修期。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]