[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117412":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117412,789,1,"单选题","某酒店建设工程将设计工作分包给一家设计单位，下列（）不属于该设计单位的项目目标",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目投资目标",false,{"key":16,"text":17,"correct":14},"B","设计进度目标",{"key":19,"text":20,"correct":21},"C","施工质量目标",true,{"key":23,"text":24,"correct":14},"D","设计成本目标","2021\u002F2020教材P4页 设计方的项目管理目标。教材原文是设计方的项目管理主要服务于项目的整体利益和设计方本身的利益。其项目管理的目标包括设计的成本目标、设计的进度目标和设计的质量目标，以及项目的投资目标。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]