[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117411":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117411,789,1,"单选题","某施工企业在基础工程施工过程中，通过采用价值工程优化了施工方案，结果在不增加施工成本的前提下，缩短了工期并提高了工程质量。这体现了项目的投资目标、进度目标和质量目标之间的()关系。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","矛盾",false,{"key":16,"text":17,"correct":14},"B","关联",{"key":19,"text":20,"correct":21},"C","统一",true,{"key":23,"text":24,"correct":14},"D","协调","2021\u002F2020教材P2页 项目的投资目标、进度目标和质量目标之间既有矛盾的一面，它们之间的关系是对立的统一关系。建设单位通过有效的管理，即通过价值工程优化施工方案，在不增加投资和不影响质量的前提下缩短了工期，这反映了目标之间统一性的一面。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]