[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117408":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117408,789,1,"单选题","下列关于施工方进行项目管理的说法，错误的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","“自项目开始至项目完成”指的是项目的实施期",false,{"key":16,"text":17,"correct":14},"B","费用目标对施工方而言是成本目标",{"key":19,"text":20,"correct":14},"C","项目实施期管理的主要任务是通过管理使项目的目标得以实现",{"key":22,"text":23,"correct":24},"D","项目实施期管理工作的主要任务是确定项目的定义",true,"2021\u002F2020教材P2页 项目决策期管理工作的主要任务是确定项目的定义，而项目实施期管理的主要任务是通过管理使项目的目标得以实现。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]