[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117404":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117404,789,1,"单选题","某工程项目施工采用施工总承包模式，其中电气设备由业主指定的分包单位采购和安装，则在施工中分包单位必须接受()的工作指令，服从其总体项目管理。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","业主",false,{"key":16,"text":17,"correct":14},"B","设计方",{"key":19,"text":20,"correct":21},"C","施工总承包方",true,{"key":23,"text":24,"correct":14},"D","项目监理方","2021\u002F2020教材P6页 若采用施工总承包或施工总承包管理模式，分包方不论是一般的分包方，或由业主指定的分包方）必须接受施工总承包方或施工总承包管理方的工作指令，服从其总体的项目管理。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]