[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117400":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117400,789,1,"单选题","自项目开始至项目完成指的是项目的()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","审批期",false,{"key":16,"text":17,"correct":14},"B","准备期",{"key":19,"text":20,"correct":21},"C","实施期",true,{"key":23,"text":24,"correct":14},"D","验收期","2021\u002F2020教材P2页 “自项目开始至项目完成”指的是项目的实施期。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]