[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117399":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117399,789,1,"单选题","下面关于总承包方管理目标和任务说法错误的是（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","主要服务于项目的利益和建设项目总承包方本身的利益。",false,{"key":16,"text":17,"correct":14},"B","管理的目标包括项目的总投资目标",{"key":19,"text":20,"correct":14},"C","管理的目标包括总承包方的成本目标、项目的进度目标和项目的质量目标。",{"key":22,"text":23,"correct":24},"D","管理的目标包括施工的成本目标、施工的进度目标和施工的质量目标。",true,"2021\u002F2020教材P5页 总承包方项目管理的目标和任务，包括项目的总投资目标和总承包方的成本目标，进度目标和质量目标D 的说法是错误的。记住，题目问的是错误的是。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]