[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117398":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117398,789,1,"单选题","按国际工程惯例，当采用指定分包商时，应对分包合同规定的工期和质量目标负责的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","业主",false,{"key":16,"text":17,"correct":14},"B","监理方",{"key":19,"text":20,"correct":14},"C","指定分包商",{"key":22,"text":23,"correct":24},"D","施工总承包方",true,"2021\u002F2020教材P6页 (3)施工总承包方是工程施工的总执行者和总组织者，它除了完成自己承担的施工任务以外，还负责组织和指挥它自行分包的分包施工单位和业主指定的分包施工单位的施工(业主指定的分包施工单位有可能与业主单独签订合同，也可能与施工总承包方签约，不论采用何种合同模式，施工总承包方应负责组织和管理业主指定的分包施工单位的施工，这也是国际惯例），并为分包施工单位提供和创造必要的施工条件。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]