[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117395":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117395,789,1,"单选题","业主方项目管理的进度目标指的是()",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","道路试运行结束",false,{"key":16,"text":17,"correct":14},"B","道路竣工结算完成",{"key":19,"text":20,"correct":14},"C","工厂通过竣工验收",{"key":22,"text":23,"correct":24},"D","工厂建成投入生产",true,"2021\u002F2020教材P2页 三、业主方项目管理的目标和任务进度目标指的是项目动用的时间目标，也即项目交付使用的时间目标，如工厂建成可以投入生产、道路建成可以通车、办公楼可以启用、旅馆可以开业的时间目标等。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]