[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117388":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117388,789,1,"单选题","建设项目工程总承包的基本出发点是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","借鉴流水线的经验",false,{"key":16,"text":17,"correct":18},"B","实现建设生产过程的组织集成化",true,{"key":20,"text":21,"correct":14},"C","克服由于设计与施工的集成致使投资增加",{"key":23,"text":24,"correct":14},"D","加快施工进度","2021\u002F2020教材P7页 建设项目工程总承包的基本出发点是借鉴工业生产组织的经验，实现建设生产过程的组织集成化，以克服由于设计与施工的分离致使投资增加，以及克服由于设计和施工的不协调而影响建设进度等弊病。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]