[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117385":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117385,789,1,"单选题","某业主欲投资建造一座五星级宾馆，业主方项目管理的进度目标指的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目通过竣工验收",false,{"key":16,"text":17,"correct":18},"B","宾馆可以开业",true,{"key":20,"text":21,"correct":14},"C","项目竣工结算完成",{"key":23,"text":24,"correct":14},"D","宾馆开始盈利","2021\u002F2020教材P2页 业主方项目管理的目标，原文是业主方项目管理服务于业主的利益，其项目管理的目标包括项目的投资目标、进度目标和质量目标。其中投资目标指的是项目的总投资目标。进度目标指的是项目动用的时间目标，即项目交付使用的时间目标，如工厂建成可以投人生产、道路建成可以通车、办公楼可以启用、旅馆可以开业的时间目标等。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]