[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117382":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117382,789,1,"单选题","关于建设工程项目管理的表述，不正确的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设工程项目管理的内涵是自项目开始至项目完成，通过项目策划和项目控制，以使项目的费用目标、进度目标和质量目标得以实现",false,{"key":16,"text":17,"correct":14},"B","自项目开始至项目完成指的是项目的实施期",{"key":19,"text":20,"correct":14},"C","项目实施期管理的主要任务是通过管理使项目的目标得以实现",{"key":22,"text":23,"correct":24},"D","项目决策期管理工作的主要任务是确定项目的工期",true,"2021\u002F2020教材P2页 项目决策期管理工作的主要任务是确定项目的定义。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]