[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117381":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117381,789,1,"单选题","以下不属于业主方在设计阶段的工作是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","初步设计",false,{"key":16,"text":17,"correct":14},"B","技术设计",{"key":19,"text":20,"correct":14},"C","施工图设计",{"key":22,"text":23,"correct":24},"D","工期设计",true,"2021\u002F2020教材P3页 图2Z101011建设工程项目的决策阶段和实施阶段设计阶段的任务包括初步设计、技术设计、施工图设计。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]