[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117375":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117375,789,1,"单选题","对专业分包企业的工作和负责的工程负有协调和管理责任,并承担由此造成损失的単位是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计单位",false,{"key":16,"text":17,"correct":14},"B","建设单位",{"key":19,"text":20,"correct":21},"C","施工总承包企业",true,{"key":23,"text":24,"correct":14},"D","监理单位","2021\u002F2020教材P6页 (3)不论是业主方选定的分包方，或经业主方授权由施工总承包管理方选定的分包方，施工总承包管理方都承担对其的组织和管理责任。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]