[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117372":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117372,789,1,"单选题","建设项目实施阶段管理工作的主要任务是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目策划",false,{"key":16,"text":17,"correct":14},"B","项目控制",{"key":19,"text":20,"correct":21},"C","通过管理使项目目标实现",true,{"key":23,"text":24,"correct":14},"D","项目定义","2021\u002F2020教材P2页 项目决策期管理工作的主要任务是确定项目的定义，而项目实施期管理的主要任务是通过管理使项目的目标得以实现.",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]