[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117369":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117369,789,1,"单选题","某建设工程项目采取施工总承包管理模式，其中的二次装饰装修工程由建设单位发包给乙单位，则在施工中，乙单位应该直接接受()的工作指令。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","设计单位",{"key":19,"text":20,"correct":21},"C","施工总承包管理企业",true,{"key":23,"text":24,"correct":14},"D","施工承包企业","2021\u002F2020教材P6页 若采用施工总承包或施工总承包管理模式，分包方（不论是一般的分包方，或由业主指定的分包方）必须接受施工总承包方或施工总承包管理方的工作指令，服从其总体的项目管理。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]