[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117359":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117359,789,1,"单选题","建设工程项目决策阶段包含的内容是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制项目建议书",true,{"key":16,"text":17,"correct":18},"B","编制设计任务书",false,{"key":20,"text":21,"correct":18},"C","施工图设计",{"key":23,"text":24,"correct":18},"D","确定项目总投资","2021\u002F2020教材P3页",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]