[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117353":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117353,789,1,"单选题","对业主方项目管理的目标而言，进度目标是指项目的()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","立项时间目标",false,{"key":16,"text":17,"correct":14},"B","竣工时间目标",{"key":19,"text":20,"correct":21},"C","项目动用的时间目标",true,{"key":23,"text":24,"correct":14},"D","运营时间目标","2021\u002F2020教材P2页 业主方项目管理的目标，原文是主方项目管理服务于业主的利益，其项目管理的目标包括项目的投资目标、进度目标和质量目标。其中投资目标指的是项目的总投资目标。进度目标指的是项目动用的时间目标，也即项目交付使用的时间目标，如工厂建成可以投入生产、道路建成可以通车、办公楼可以启用、旅馆可以开业的时间目标等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]