[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117349":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117349,789,1,"单选题","某学校拟新建一科教综合楼，经设计招标，由甲设计公司承担该项目设计任务。下列不属于该设计院项目管理目标的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目的投资目标",false,{"key":16,"text":17,"correct":14},"B","设计的成本目标",{"key":19,"text":20,"correct":14},"C","设计的进度目标",{"key":22,"text":23,"correct":24},"D","项目的进度目标",true,"2021\u002F2020教材P4页 设计方作为项目建设的一个参与方，其项目管理主要服务于项目的整体利益和设计方本身的利益。其项目管理的目标包括设计的成本目标、设计的进度目标和设计的质量目标，以及项目的投资目标。项目的投资目标能否实现与设计工作密切相关。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]