[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117311":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":15,"analysis":23},1117311,789,1,"单选题","根据九部委《标准施工招标文件》，关于施工合同变更程序的说法，正确的是（ ）。 A.承包人书面报告发包人后，可根据实际情况对工作进行变更 B.承包人根据合同约定，可以向监理人提出书面变更建议 C.发包人可以直接向承包人发出变更意向书 D.监理人应在收到承包人书面建议后30 天内做出变更指示",[11,14,17,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":16},"B",true,{"key":18,"text":18,"correct":13},"C",{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":13},"E","根据《标准施工招标文件》中通用合同条款的规定，在履行合同过程中，承包人对发包人提供的图纸、技术要求以及其他方面提出的合理化建议，均应以书面形式提交监理人。",{"id":6,"name":25,"category":26,"favorite":27},"二建建设工程施工管理","建筑工程",0]