[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117309":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":15,"analysis":23},1117309,789,1,"单选题","下列合同实施偏差分析的内容中，不属于合同实施趋势分析的是（）。 A.总工期的延误 B.项目管理团队绩效奖惩 C.总成本的超支 D.最终工程经济效益水平",[11,14,17,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":16},"B",true,{"key":18,"text":18,"correct":13},"C",{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":13},"E","针对合同实施偏差情况可以采取不同的措施，应分析在不同措施下合同执行的结果与趋势，包括:(1)最终的工程状况，包括总工期的延误、总成本的超支、质量标准、所能达到的生产能力(或功能要求)等;(2)承包商将承担什么样的后果，如被罚款、被清算，甚至被起诉，对承包商资信、企业形象、经营战咯的影响等:(3)最终工程效益(利润)水平。",{"id":6,"name":25,"category":26,"favorite":27},"二建建设工程施工管理","建筑工程",0]