[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117308":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":23},1117308,789,1,"单选题","根据《标准施工招标文件》通用合同条款，承包人应该在收到变更指示最多不超过（ ）天内，向监理人提交变更报价书。 A.14 B.7 C.28 D.30",[11,14,17,19,21],{"key":12,"text":12,"correct":13},"A",true,{"key":15,"text":15,"correct":16},"B",false,{"key":18,"text":18,"correct":16},"C",{"key":20,"text":20,"correct":16},"D",{"key":22,"text":22,"correct":16},"E","除专用合同条款对期限另有约定外，监理人收到承包人变更报价书后的14 天内，根据合同约定的估价原则，按照总监理工程师与合同当事人商定或确定变更价格。",{"id":6,"name":25,"category":26,"favorite":27},"二建建设工程施工管理","建筑工程",0]