[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117307":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":23},1117307,789,1,"单选题","某工程施工过程中，为了纠正出现的进度偏差，承包人采取了夜间加班和增加劳动力投入措施。该措施属于纠偏措施中的（ ）。 A.技术措施 B.经济措施 C.合同措施 D.组织措施",[11,14,16,18,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":13},"C",{"key":19,"text":19,"correct":20},"D",true,{"key":22,"text":22,"correct":13},"E","合同实施偏差处理 （1）组织措施，如增加人员投入，调整人员安排，调整工作流程和工作计划等； （2）技术措施，如变更技术方案，采用新的高效率的施工方案等； （3）经济措施，如增加投入，采取经济激励措施等； （4）合同措施，如进行合同变更，签订附加协议，采取索赔手段等。",{"id":6,"name":25,"category":26,"favorite":27},"二建建设工程施工管理","建筑工程",0]