[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117306":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":23},1117306,789,1,"单选题","某工程由于图纸、规范等准备不充分，招标方仅能制定一个估算指标，则在招标时宜采用成本加酬金合同中的（ ）。 A.成本加固定费用合同 B.成本加固定比例费用合同 C.成本加奖金合同 D.最大成本加费用合同",[11,14,16,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",true,{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":13},"E","在招标时，当图纸、规范等准备不充分，不能据以确定合同价格，而仅能制定一个估算指标时可采用这种形式。黑钻押题，金考典软件考前更新，下载链接 www.jinkaodian.com",{"id":6,"name":25,"category":26,"favorite":27},"二建建设工程施工管理","建筑工程",0]