[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117305":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117305,789,1,"单选题","关于单价合同的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对于投标书中出现明显数字计算错误时，评标委员会有权先做修改再评标",true,{"key":16,"text":17,"correct":18},"B","单价合同允许随工程量变化而调整工程单价，业主承担工程量方面的风险",false,{"key":20,"text":21,"correct":18},"C","单价合同分为固定单价合同、变动单价合同、成本补偿合同",{"key":23,"text":24,"correct":18},"D","实际工程款的支付按照估算工程量乘以合同单价进行","单价合同的特点是单价优先，而实际工程款则按实际完成的工程量和承包商投标时所报的单价计算。对于投标书中明显的数字计算错误，业主有权力先作修改再评标，当总价和单价的计算结果不一致时，以单价为准调整总价。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]