[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117299":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":15,"analysis":23},1117299,789,1,"单选题","下列合同计价方式中，对承包商来说风险最小的是（ ）。 A.单价合同 B.成本加酬金合同 C.固定总价合同 D.变动总价合同",[11,14,17,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":16},"B",true,{"key":18,"text":18,"correct":13},"C",{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":13},"E","",{"id":6,"name":25,"category":26,"favorite":27},"二建建设工程施工管理","建筑工程",0]